Latest AACE-PSP Exam Premium Dumps provide by TrainingQuiz.com to help you Passing AACE-PSP Exam! TrainingQuiz.com offers the updated AACE-PSP exam dumps, the TrainingQuiz.com AACE-PSP exam questions has been updated to correct Answer. Get the latest TrainingQuiz.com AACE-PSP pdf dumps with Exam Engine here:
(218 Q&As Dumps, 40%OFF Special Discount: DumpsDB)
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
Correct Answer: C
Question 82
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
Correct Answer: C
To constrain a project's end date, a Finish-No-Later constraint is applied to the last activity. This ensures any slippage results in negative float, signaling delays relative to the fixed deadline. Option A and B apply to earlier constraints, which are not relevant for controlling the project's end date. Option D applies a constraint to the first activity, not the project finish. This concept aligns with controlling project deadlines as described in the PSP Study Guide.
Question 83
A driving relationship is _____________________.
Correct Answer: D
A driving relationship is the dependency link where the predecessor activity directly governs the dates of the successor activity. Option A confuses "driving" with critical path relationships. Option B oversimplifies by focusing on one type of relationship. Option C is vague and does not specify the control aspect. The driving relationship determines schedule flow and is essential for maintaining logical dependencies in CPM scheduling.
Question 84
If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?
Correct Answer: A
* Understanding the Problem Context: Activity C is currently set to complete on Day 40. Activity A has a 5-day delay in starting, so adjustments are needed to maintain the Day 40 completion date for Activity C. The key is to identify which adjustment will fail to maintain the timeline. * Option-by-Option Analysis: A . Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from 'B' to 'C' with FSO (Finish-to-Start with Offset): Reducing Activity A's duration from 20 to 10 days might mitigate part of the delay, but replacing the relationship between B and C with FSO introduces an offset. FSO relationships typically delay the start of successor activities (Activity C in this case). This would likely push Activity C beyond Day 40 because the delay in B's finish, coupled with the offset, would result in C starting later. This adjustment does NOT maintain the completion date of Activity C. B . Replace the relationship from 'B' to 'C' with SSO (Start-to-Start with Offset): An SSO relationship allows Activity C to begin once Activity B starts (with or without an offset). This adjustment effectively overlaps the schedules of B and C, mitigating delays from A. This adjustment can maintain the completion date of Activity C at Day 40. C . Reduce the duration of 'B' from 10 days to 5 days by compressing work effort: Reducing B's duration by compressing its schedule shortens its timeline, allowing Activity C to start sooner. This adjustment offsets the delay caused by Activity A. This adjustment can maintain the completion date of Activity C at Day 40. * Final Answer and Justification: The adjustment described in A will NOT maintain the completion date of Activity C at Day 40 because the FSO relationship introduces delays, making it ineffective in this scenario. Options B and C offer feasible adjustments to maintain the timeline. * Study Guide Reference: Refer to the PSP Certification Study Guide, Chapter 2 - Scheduling, Subchapter 2.2.4: Relationships (p. 151-157), which details the impact of logical relationships (FSO, SSO) on schedule timelines. Additionally, review AACE Recommended Practice 52R-06: Time Impact Analysis for insights into how delays affect dependent activities and methods for mitigating them.
Question 85
Resource planning must take all of the following into account except for