Question 6
Gather the information needed by the shop floor to make the product. Release orders to the shop floor as authorized by the material equipment plan. This is called dispatching. Production activity control will do such things in:
Question 7
Based on material flow, processes can be organized in which way?
Question 8
What is a problem for manufacturing, but it can be attained by overtime or under-time, shifting workers, and so forth?
Question 9
If the opening inventory is 400 units, demand is 900 units, and production is 800 units, what will be the ending inventory?
Question 10
MRP and CRP should form part of a/an?