A business analyst has interviewed project stakeholders and has a robust list of requirements.
At which stages in the requirements engineering framework would he check that these requirements support the business objectives defined at the start of the project?
A business analyst is in the process of validating a set of requirements produced for a new business initiative and the following needs agreement:
That the requirements...
1) Are within the scope of the project.
2) Can be verified when they have been implemented.
3) Express business needs clearly and correctly.
Who is responsible for this agreement?
During his yearly appraisal, a member of the sales team is given the following feedback:
'Your approach to your sales target has been successful, but you have not applied the approach widely enough. Your target for next year is to use your recent experience to double your sales- this will ensure your contribution is in line with the team's increased target'.
After discussion, this target is agreed on and is added to his written appraisal.
The organization recognizes four facets of knowledge:
(A) Individual
(B) Corporate
(C) Explicit
(D) Tacit
Which combination describes the appraisal target given above?
Below is a requirements list for a taxi company's booking system:
REQ#1: The system must allow the operator to make and amend a taxi
booking.
REQ#2: The system must allow the operator to delete a taxi booking.
REQ#3: The system must be available within standard working hours.
REQ#4: The system should support 100 concurrent booking requests
between 06:00hrs and 23:30hrs.
REQ#5: The system should allow the operator to add a note when
cancelling a taxi booking.
The following actions are being considered:
(A) Separate REQ#1 into 2 requirements.
(B) Clarify what is meant by 'standard working hours' in REQ#3.
(C) Check that the proposed solution will be able to support 100
concurrent booking requests, per REQ#4.
(D) Separate REQ#4 into 2 requirements.
(E) Review and merge REQ#2 and REQ#5.
Which of these actions should be undertaken to improve the clarity of these requirements?
Make Me A Star Productions runs an annual talent competition for aspiring amateur singers.
Four business rules have been identified:
1) A contestant is allowed to sing 1 or 2 songs in a performance.
2) An audition may be attended by up to 50 contestants.
3) A contestant is always given an audition.
4) A song can only be used in one performance.
Which of these business rule(s) can be found to be correctly represented in the class diagram?