Question 36
Blakenall District Hospital (BDH) is a large hospital that is a major part of the government's health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy has caused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?
Question 37
Standard terms and conditions should become the governing terms for which group of items?
Question 38
Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?
Question 39
Which of the following indicates the ratio between profit and costs?
Question 40
To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?