Which of the following are true statements about RFQ process? Select TWO that apply.
Correct Answer: A,D
Request for quotations is often used when the only variable is price and the purchase value is under a financial threshold. This process is less formal than ITT. RFQ should be used in the following circumstances: - Low-value, low-risk purchases - When the specifications are sufficiently defined or the product/service is standardised - Where the suppliers are pre-qualified - Where there is a framework agreement which specifies the contract terms and conditions. Reference: LO 1, AC 1.1
Question 7
Which of the following should be specially noticed in market dialogue with suppliers in specification development?
Correct Answer: A
Being clear on your objectives helps you to design the best approach to the dialogue. There are some notices in developing dialogue with suppliers: - All meetings should be documented - Respect commercial confidentiality. Although insights gained from one conversation lead to questions in another, you must be very careful not to allow this to happen in a way that breaches the confidentiality of the first conversation. Reference: CIPS study guide page 84-85 LO 2, AC 2.1
Question 8
Which of the following is the most suitable model contract for car lift manufacturing?
Correct Answer: C
IMechE/IET: Institution of Mechanical Engineers/Institution of Engineering and Technology - two separate institutes that issue jointly agreed model forms covering the design, supply and installation of electrical, electronic and mechanical plant including special conditions for the ancillary development of software. Car lifts are mechanical products, so IMechE/IET is the most suitable model contract for this type of product. FIDIC is a French language acronym for Federation Internationale Des Ingenieurs-Conseils, which means the international federation of consulting engineers. It was started in 1913 by the trio of France, Belgium and Switzerland. The United Kingdom joined the Federation in 1949. FIDIC is headquartered in Switzerland and now boasts of membership from over 60 different countries. FIDIC published its first contract, titled The Form of contract for works of Civil Engineering construction, in 1957. As the title indicated, this first contract was aimed at the Civil Engineering sector and it soon became known for the colour of its cover, and thus, The Red Book. It has become the tradition that FIDIC contracts are known in popular parlance by the colour of their cover. This first contract by FIDIC was undertaken jointly with the International federation of Building and Public works. FIDIC's concerted effort at achieving broad consultation and acceptance of its contract forms has seen subsequent editions of its contracts being ratified by the International Federation of Asian and Western Pacific Contractors Association, Associated General Contractors of America and the Inter-American Federation of the Construction Industry, Multilateral Development Banks among others. Because of the broad support it enjoys, FIDIC contracts are the foremost contracts in international construction. The Chartered Institute of Procurement and Supply (CIPS) has some model contracts for IT functions including: supply and installation of computer equipment, support and maintenance of bespoke software, servicing of computer equipment,... The International Trade Centre (ITC) produces contracts specifically designed for small companies doing international business, covering the sale of goods, distribution, services and joint ventures. Reference: CIPS study guide page 142 LO 3, AC 3.1
Question 9
A senior buyer is preparing specification for the next purchase. He intends to embed social and environmental criteria that align with his organisation's overarching strategy. Which of the following provides the social and environmental objectives that an organisation pursues?
Correct Answer: D
The organisation should have an overarching strategies or policies which sets out the social and environmental objectives to be pursued via procurement and the supply chain generally. Some of these will be about the specification, but that must be tied in other aspects of the sourcing strategy. These objectives, policies and strategies can be found in corporate social responsibility policy. Reference: CIPS study guide page 96 LO 2, AC 2.1
Question 10
Which of the following statement is true about one-off contract?
Correct Answer: B
One-off contract is the type of contract that relates to a single purchase. One-off contracts can be used for goods, services or works. One-off contract can be simple (such as buying a small number of office stationeries) or complex (such as a construction project or buying an aircraft). A one-off contract lasts "until completion of the obligations of the parties". The performance is unlikely to be improved during contract performance since the duration is relatively shorter than framework agreement or call-off contract. Ad-hoc purchase is an item bought for a single and non-recurring use or purpose. Ad-hoc purchase is a type of one-off contract. Reference: LO 1, AC 1.3