Question 86
Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1,
and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C.
Which of the following is the critical path if Task B starts on Day 3?
Question 87
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
Question 88
A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
Question 89
A project sponsor decides to cut the project budget and reduce the scope. As a mitigation plan, the team decides to promote the project internally to gain support from other areas.
Which of the following describes the BEST combination of communication methods that can be used to attract more people?
Question 90
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week Which of the following should the project manager do
NEXT?