Question 216
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).
Question 217
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
Question 218
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A.
Task D and E start after Task C.
If Task A starts on December 15, which of the following is the anticipated start date for Task D?
Question 219
A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
Question 220
An approved change was implemented. Which of the following should be accomplished NEXT?