Question 51
An architect is proposing a solution that has two HPE Moonshot 1500 chassis, each of which is full of m700 cartridges. The customer needs the solution to quickly deploy the OS to cartridges, back up a golden node image. and clone the image.
The customer is concerned about cost and is not interested in managing or monitoring performance of the solution,
Which solution meets these requirements?
Question 52
A customer is planning to migrate from a Virtual Connect Enterprise Manager (VCEM) environment to HPE OneView.
Which topic should the architect discuss with the customer before the migration is implemented?
Question 53
An architect is planning an HPE Moonshot System deployment. The architect plans to individually connect each iLO CM module to the management network. The customer informs the architect that this plan requires too many 1GbE ports per rack for the data center infrastructure.
What is one way that the architect can alter the plan to meet the customer's needs, while still allowing iLO access to the HPE Moonshot Systems?
Question 54
An architect is proposing a solution that has two HPE Moonshot 1500 chassis, each of which is full of m700 cartridges. The customer needs the solution to quickly deploy the OS to cartridges, back up a golden node image. and clone the image.
The customer is concerned about cost and is not interested in managing or monitoring performance of the solution,
Which solution meets these requirements?
Question 55
An architect is proposing a solution that has two HPE Moonshot 1500 chassis, each of which is full of m700 cartridges. The customer needs the solution to quickly deploy the OS to cartridges, back up a golden node image, and clone the image.
The customer is concerned about cost and is not interested in managing or monitoring performance of the solution.
Which solution meets these requirements?