Question 146
A project to replace an old sales and merchandising system with a new version based on modern platforms, will use an Agile lifecycle with iterations of fixed length.
The project objectives include:
* Delivery within 6 months of the start of the first iteration, in 3 releases, to be accomplished by a team that will contain all resources deemed necessary to achieve this
* Quality of delivered product to meet customer acceptance criteria
A test objective, derived from discussion with the customers, has been set as follows:
"Each release shall deliver usability that is better than that of the previous system for the equivalent functionality" Which S.M.A.R.T. criteria are met by this objective?
* Specific
* Measurable
* Achievable
* Relevant
* Timely
Question 147
You are interviewing a candidate for the position of test analyst. At one stage of the interview, you are looking specifically for skills in the area of professional competence. Which of the following skills would demonstrate this?
Question 148
As a Senior Test Manager for a large UK based software company, you have been tasked with setting up an outsourced test facility in another country and another time zone. Test effort will be equally split between the UK and the outsourced test facility.
Which of the following factors is MOST LIKELY to lead to the success of the new working arrangement?
a. Introduce clearly defined lines of communication.
b Increase the use of informal test execution.
c Align the testing methodologies used at each site
d. Implement a weekly team meeting where reps from each site attend in person.
e. Increase the overlap of allocated testing tasks.
f. Introduce local defect management processes for each site.
Question 149
As a Test Manager, which one of the following do you think is the MOST important reason for ensuring effective processes are in place for test monitoring and reporting?
SELECT ONE OPTION
Question 150
In what way is the operations team usually Involved In testing7