You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?
Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units
and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50
percent on the task. You change John's assignment units to 50 percent for the task.
Which set of values describes the specified task?
You need to create a project plan that accommodates the corporate holiday calendar. What should you do?
You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?