Your company uses Microsoft Project, and you are setting up an initial planning schedule.
You need to make sure that all new task durations are shown as estimated.
What should you do?
Your organization uses Project Professional 2013.
You are setting up a preliminary schedule by using manually scheduled tasks.
As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.
You need to determine the cause of the wavy red line.
What should you do?
You are a project manager who uses Project Professional 2013.
You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013.
You use milestones as key deliverables, and you use summary tasks as phases.
Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.
You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.
What should you do?
You are a project manager who uses Project Standard 2013.
You regularly customize the Bar Styles for a project prior to printing the project schedule.
You need to add the Bar Styles button to the Quick Access Toolbar as quickly as possible.
What are two ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
Your company uses Project Professional 2013.
You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the projects so that Project
1 is the highest priority project and gets all the required resource availability first. Project 2 then gets resources as they become available from Project 1.
You need to maintain this priority throughout the execution of the project.
What should you do?