You are a project manager who uses Project Professional 2013.
You manage a software development project and have baselined the project. Your Project Management Office (PMO) requires you to capture the actual hours per resource for each task in your project schedule. You use these weekly actual hours to generate a weekly report for your project sponsor.
Your resources report their actual hours each Friday.
You need to enter the hours in your Project Schedule on a weekly basis.
What should you do?
DRAG DROP
You are a project manager who uses Project Standard 2013.
Your project is approved, and you identify named resources to replace the generic resources for your project tasks.
You need to update the project schedule to assign the named resources to their appropriate tasks.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?
You are a project manager who uses Project Professional 2013.
You have created a project which involves three other colleagues who are also using Project Professional 2013. You and your colleagues are over budget and cannot spend any more money on this project.
To ensure that the latest version of the project file is always the one being used, you need to save, share, and sync this project plan File among your colleagues without using email.
What should you do?
You are a project manager who uses Project Professional 2013.
When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table.
You discover that many of the tasks have negative Total Slack values.
You need to resolve the negative Total Slack values.
What should you do?