HOTSPOT
You are a project manager for an organization that is using Microsoft PPM to manage projects. Projects are staffed using the enterprise resource pool.
You assign a resource to a task and set the value of Work hours to 10. You assign no overtime hours.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.
Use the drop-down menus to select the answer choice that answers each question.
You are a project manager for an organization that is using Microsoft Project.
You have enabled Single Entry Mode and team members update their task using timesheets.
You need to see how these updates impact your project before you approve the tasks.
What should you do?
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.