You are a project manager who uses Project Professional 2013.
Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Project Professional 2013.
The standard Project Professional 2013 report views named Late Tasks and Milestone Report already have all the information required for the new model.
You are assigned to consolidate the information from these two reports into a dashboard view named Status Report Model. Your organization wants to keep the same format, colors, and layout.
You need to implement this solution.
What should you do?
You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?
While scheduling with Project Professional 2013 you notice that there are three days of remaining duration on the Database Design task.
The resource performing this task indicates that the work is completed.
You need to update the schedule to reflect this change.
What should you do?
You manage a project and use Project Professional 2013 to track your project schedule.
One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned at
50% of their availability.
The resource asks to start the task three days later than planned because of a scheduling conflict. The schedule change is approved.
You need to make the adjustment to the resource assignment to accommodate this request without affecting the other resources assigned to the task.
What should you do?