Free Microsoft 74-343 Exam Dumps Questions & Answers
| Exam Code/Number: | 74-343Join the discussion |
| Exam Name: | Managing Projects with Microsoft Project 2013 |
| Certification: | Microsoft |
| Free Question Number: | 110 |
| Publish Date: | Aug 06, 2026 |
| # of views: | 3355 |
|
|
|
You are a project manager for a software development company that uses Project Professional 2013.
For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes. Additionally, your company's status reports of project progress are based on Work and Cumulative Work.
Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.
You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.
What should you do?
You are using Project Standard 2013.
Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.
You need to show one line item that displays all the requested information in the Gantt view.
What should you do?
DRAG DROP
You are a project manager who uses Microsoft Project 2013.
A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time.
You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
You are managing a project by using Project Professional 2013, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column.
You need to resolve the issue.
What should you do?
