In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
An architect is working on a design-build project for a large skyscraper. The architect has completed a conceptual design, finalized the contracts, and hired consultants. The schematic design phase is set to begin in one week.
Which items or tasks are important for the architect to complete during this time? Check the three that apply.
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?

Refer to the exhibit.
The following changes occur during the project:
* The owner delayed the project kickoff until September Year 1 due to delays in finalizing the Owner- Architect Agreement.
* The architect did not have enough staff available to start the project on time, so the firm hired temporary staff for 2 months.
* The owner made a design change in January Year 2 that added 2 weeks to the schedule.
* Not enough bids were received, and the project was bid a second time with additional advertising.
* The owner made design changes in May and July of Year 2 that each added 3 weeks to the schedule.
When were the construction documents completed based on the project changes?