Question 21
After imaging the nodes and creating the cluster successfully, the consultant connects the cluster to the customer network. When logging into Prism, the events dashboard is full of errors.
What is causing the issue?
Question 22
A consultant finishes creating a new ESXi cluster. The consultant connects to the nodes via laptop and a personal flat switch. The host/CVM network is on VLAN 23. The customer has the native VLAN on the ToR switches set to 23.
The customer wants to use LACP. Before placing the nodes on the customer network, the consultant tags VLAN 23 for each host and CVM. The consultant connects the nodes to the customer network and finds that they are unreachable.
What is causing this issue?
Question 23
In a 20-node ESXi deployment, the customer needs additional resiliency to survive the loss of two nodes concurrently.
Which configuration should the consultant use to ensure that the appropriate resources are available?
Question 24
A consultant is setting up a new Hyper-V cluster. The customer requirements are as follows:
* VMs should automatically failover to another host if the host crashes
* Host CPU and Memory resources should be evenly balanced
* New VMs should be placed on the host with the most resources available Which two Hyper-V features can be used to meet the requirements? (Choose two.)
Question 25
A consultant successfully completes a Foundation using a flat switch. The consultant then works with the customer to move the cluster over to their production network. After the move, the CVMs and hypervisors can no longer communicate, which prevents the cluster from starting.
Which option should be used to resolve this issue?