Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.
(Choose the best answer.)
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
Your customer accounts revenue based on, product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category "Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)
Which precedence order is used by the system for labor schedules to distribute payroll cost?