A Work Center created a month ago is no longer in use now. You want to remove the Work Center; however, the system is no allowing you to delete it.
Identify three reasons for this.
A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs.
Identify the two recommendations.
The Manufacturing Engineer, responsible for creating and maintaining the Work Definitions, has scheduled the Process Item Structure Changes to Work Definitions program. However, after the execution of the program the engineer did not receive a notification with the details of the Item Structure changes.
Which two reasons could cause this?
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.