Free PMI PMI-RMP Exam Dumps Questions & Answers
| Exam Code/Number: | PMI-RMPJoin the discussion |
| Exam Name: | PMI Risk Management Professional |
| Certification: | PMI |
| Free Question Number: | 267 |
| Publish Date: | Jan 08, 2026 |
| # of views: | 5527 |
|
|
|
At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.
How should the risk manager respond to this comment?
The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?
A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?
After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?
Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
| PMI-RMP Dumps Other Version | QA's | Publish Date |
| PMI.PMI-RMP.v2022-07-17.q232 | 232 | Jul 17, 2022 |