A team is using a predictive model to determine possible cost overrun scenarios for a disruptive technology project. The data being used is pooled from various projects implemented within the organization.
What should the project manager do to increase accuracy?
Health Records Modernization at Hospital Case Study
A project manager led a health records modernization project at a hospital with a project budget of $US5 million and an 18-month timeline. The project involved multiple stakeholder groups including medical, administrative, and IT staff; board members; patients; insurance companies; external vendors; regulatory bodies; and union representatives.
Stakeholder management was complex and a major undertaking for the project manager, but it was critical to achieve a positive project outcome. When the project started, the project manager conducted stakeholder analysis, using the information to create both a power/interest and an influence/impact matrix. The analysis showed that while the hospital board members and regulatory bodies had high power but moderate interest, the medical staff (doctors and nurses) had both high influence and high impact on the project. Administrative staff showed high interest but lower power, while patients and insurance companies had moderate interest and varying levels of influence. Based on the analysis, the project manager created a stakeholder engagement strategy that documented expectations, communication preferences, and influence levels in a stakeholder register. The project manager also made a RACI (responsible, accountable, consulted, informed) chart to show roles and responsibilities; and created communication channels and frequency for each stakeholder group, an issue escalation system, and a feedback system for continuous stakeholder input.
To execute the modernization process of health records, the project manager realized that medical staff members would need to change their daily workflows. To facilitate change management for these stakeholders, the project manager created a clinical advisory committee, appointed department-specific
"champions," created focus groups for requirements gathering, started a training program, and developed key performance indicators (KPIs) to measure satisfaction.
During project execution, several challenges emerged. The doctors expressed concerns about the system's impact on patient care, the nurses' union raised workload concerns, the IT department faced resource constraints, the insurance companies requested additional features, and the administrative staff worried about data security. The project manager responded to these challenges by increasing the frequency of stakeholder meetings, implementing a change management program, creating a beta system for stakeholder testing, developing contingency plans for various stakeholder scenarios, and establishing an issue resolution process.
Despite these mitigation efforts, the medical staff required additional training, leading to a change request for a 2-month extension and a 10% budget increase. The board of directors approved this to help ensure high adoption and satisfaction rates among staff members. The project helped establish new good practices in future programs for stakeholder management in the organization's project management office (PMO). The documented lessons learned became a reference for future projects of similar scope and complexity.
The project manager leading the project to modernize health records in a hospital has a particular concern about clinical stakeholders-the doctors and nurses. As part of the stakeholder engagement plan, the project manager created the clinical advisory committee.
What was the objective of the project manager's action?
(Refer to the Health Records Modernization at Hospital Case Study exhibit.)
In a company with a project management office (PMO), the project manager is preparing to communicate the status of an electronic health record (EHR) implementation project to both the project team and key stakeholders. What should the project manager do to communicate the project status effectively?
During the first sprint review, the project sponsor requests an update to the product backlog. The team realizes that this may cause short-term resource constraints, but no additional budget is available.
What should the project team do?
A project team provided estimates for a hybrid project, but in every case those estimates were undervalued.
On the current trajectory, the project will not meet its
intended value before it runs out of budget.
What should the project manager do?
| PMP Dumps Other Version | QA's | Publish Date |
| PMI.PMP.v2026-09-12.q131 | 131 | Sep 12, 2026 |
| PMI.PMP.v2026-04-20.q999 | 999 | Apr 20, 2026 |
| PMI.PMP.v2024-05-18.q999 | 999 | May 18, 2024 |
| PMI.PMP.v2023-06-05.q173 | 173 | Jun 05, 2023 |
| PMI.PMP.v2022-11-03.q487 | 487 | Nov 03, 2022 |
| PMI.PMP.v2022-07-27.q469 | 469 | Jul 27, 2022 |
| PMI.PMP.v2022-06-04.q436 | 436 | Jun 04, 2022 |
| PMI.PMP.v2022-06-02.q955 | 955 | Jun 02, 2022 |