Question 101
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Question 102
Which are reasons for a benefits management approach?
1. To state how improvements will be measured
2. To confirm that the benefits are realized
3. To estimate the costs of improvement
4. To define the reason for delivering the improvement
Question 103
Why is the 'learn from experience' principle applied to a project?
Question 104
To meet the minimum requirements for applying the progress theme, what must be considered?
Question 105
Which product documents the information needed to demonstrate continued business justification?