Question 6
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
Question 7
Which is a purpose of the Controlling a Stage process?
Question 8
Which should be provided by corporate or programme management before the Starting up
a Project process commences?
Question 9
What is the collective name for individuals or groups who may be affected by a project?
Question 10
Which is a purpose of a Project Brief?