Question 211
What product is used to maintain a record of those who have an interest in the project and their information requirements?
Question 212
Which is a purpose of the Initiating a Project process?
Question 213
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Question 214
What product defines the reporting requirements between the Project Manager and Team Manager?
Question 215
Which describes an off-specification?