Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?
The Smart Meter Programme is in Tranche 2 and the Customer Processes Project is delivering ahead of schedule. This means that fewer resources are required to complete the project. The Training Project, which was due to start in Tranche 3, has now become a higher priority and needs to be started early. The programme manager has recommended starting the Training Project now although Tranche 2 and Tranche 3 will then overlap.
Is this an appropriate application of the structure' theme, and why?