Question 21
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
Question 22
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.
Question 23
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
Question 24
How are earliest dates and latest dates of activities scheduled?
Question 25
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.