Question 16
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
Question 17
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
Question 18
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
Question 19
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.
Question 20
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.