Question 1
You set up a material as a phantom assembly by entering the special procurement key in the material master.
How can you switch off the phantom assembly in a specific bill of material (BOM)?
Question 2
What does forecasting in demand planning cycle include?
Question 3
An issue storage location was NOT found through the work center, bill of material(BOM) item, or material master. What determines whether the storage location can be derived from the production version?
Question 4
You want to create a production order from a planned order. What methods could you use?
Question 5
You want to insert an operatio at a certain time on work center. The planning direction is forward. The disired dispatching time concides with an operation that has previously been dispatched. How does the insertion take place?