You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
In SAP ECC, you calculate the standard available capacity for a work center capacity using the followingdata:
-Start: 7:00:00 a.m. -End:3:00:00 p.m.
-Break duration: 1 hour
-Rate of utilization: 80% -Overload:110%
-Number of individual capacities: 1
How large is the standard available capacity?
In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot).
What could be the reason?