Question 56
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board
Question 57
Where can you define that a network is a "header-account assigned" or "activity-account assigned"?
Question 58
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.
What is the status that must be set before you can enter actual start and actual end dates?
There are 2 correct answers to this question.
Response:
Question 59
What are the different procurement types you can choose between if you choose direct procurement with item category N?
There are 2 correct answers to this question.
Response:
Question 60
In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?
Please choose the correct answer.
Response: