Question 16
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
Question 17
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
Question 18
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
Question 19
Which data object can be updated with the scheduling results of a routing?
Please choose the correct answer.
Response:
Question 20
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.