Beth is a Scrum Master over a newly formed team. What can Beth expect as the team matures in the project?
Van is the Product Owner for the JK Project. He's asked you for help in prioritizing the items in the product backlog. How should Van ordered the user stories in the Product Backlog?
Which of the following is a tool that can be used for communicating information related to risks?
While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are those primary factors?
A) Value
B) Dependencies
C) Risk
D) Deliverables
Which one of the following is an output of Sprint Planning and is used to give the Development Team a Sprint target?