Question 1
According to the nature of use, management requirements and the degree of loss or impact caused by the interruption of the operation of the electronic information system due to the failure of the site equipment, the data center is divided into () levels.
Question 2
The investment model of the cloud IDC project government is as follows. (Multiple choice)
Question 3
Resource preparation is one of the most important links before the implementation of the data center project, and it also directly determines the quality and progress of the construction. Generally, preparation is made from the following five points of man, machine, material, law and ring.
Question 4
SmartNOS is a unified brand for improving services, what service products are included? (Multiple choice)
Question 5
Huawei customer support service capabilities include the following types () (multiple choice)