Question 11
Testing and Debugging are key activities in the software development lifecycle.
Which of the following are DEBUGGING activities?
a) Designing tests to find failures.
b) Locating the cause of failures.
c) Analysing and fixing the defects.
d) Executing tests to show failures.
Question 12
Which of the following are triggers for Maintenance testing?
a) System migration from one platform to another.
b) Retirement of a system.
c) Preparation for an audit of a system.
d) Modifications to a system.
e) Development of a whole new system.
Question 13
Which of the following BEST describes a methodical approach to the Error Guessing test technique?
Question 14
Your agile project has scheduled a final sprint before release to fix and re-test all open defects with a priority level of 3 or above.
The following defect report shows the defect fields that are currently being captured on the system.
Title: Unable to add excursions to pre-paid cruises
Date raised: 21/05/18
Author: Emma Rigby
Status: Fixed
What occurred: I went to book an excursion for a pre-paid cruise but received an error message saying,
'Facility not available'. I can book excursions on cruises that have not yet been fully paid.
What should have occurred: Requirement 3.12 says clearly that customers can add excursions after cruises have been fully paid so the facility should have been available (when an additional amount may now need to be paid).
Priority: 2
Software build: 2.1
Test level: System test
Environment details: System test 3
Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint team to add?
Question 15
Which one of the following statements about techniques for estimating test effort is correct?