Question 131
You are a manufacturing consultant helping a client test out different bill of material (BOM) and route consumption options when starting production orders. Material and labor consumption are to be completed before Report as finish.
You are running a production order with BOM lines that have a Flushing principle set to Start. The Automatic Route Consumption Runtime has been set to Yes.
You have set up the default Start user options for all production orders as shown in the exhibit below.

Question 132
A company produces homeopathic lotions for pain relief and uses Dynamics 365 Supply Chain Management.
You have replaced the vendor of a product's active ingredient with a new vendor. The new vendor is supplying the ingredient at a higher concentration of 25 percent.
The previous vendor concentration was 15 percent. You are consistently running out of two of the complimentary ingredients.
You need to update the formula and ingredient settings to allow for better order planning.
What should you do?
Question 133
You are the product manager at a paint manufacturing company. Paint base is produced in 100 gallon batches.
The paint base can be packaged in 1 gallon, 5 gallon, and 10 gallon containers.
You want to use consolidated batch orders for the bulk paint base item. You need to set up the items and formulas to allow for consolidated batch orders.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Question 134
A company uses Discreet manufacturing concepts to produce cables. The company's production scheduler uses internal documents to track issues on in-process production orders.
The production scheduler must group all in-process production orders according to issues. The scheduler must be able to easily determine issues with production orders.
You need to implement a method to easily identify production orders with issues.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Question 135
You are the production planner for a manufacturing company.
After running operations scheduling for a production order, the following error message displays:
You need to identify the cause of the error.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.