Question 56
A manufacturer uses discreet orders and manually consumes raw material after reporting products as finished.
You are performing an end-of-month closing for remaining picking lists on production orders. You must not be required to consume the full amount of material on production order picking lists as a result of improved production efficiency. When the production manager verifies that no material is left to consume, there are remaining back-ordered amounts.
You need to pick the line item short and eliminate the remaining demand.
What should you do?
Question 57
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
Question 58
A company manufactures and sells speaker boxes. The speaker boxes can be silver or black with a basic or upgraded wiring harness assembly.
The speaker box must be created in the item master so that the variables for colors and harness type can be assigned at order entry.
You need to create a new item that supports multiple variables.
What should you do?
Question 59
A company that produces rubber hose using Discreet orders accounts for raw material scrap after report as finished though inventory movement journals.
The company has noticed that most of the scrap that is recorded is due to start up that feeds the hose to the finishing process. In addition, the amount of scrap that is recorded is consistent regardless of the amount of hose being produced.
You need to account for material lost during startup.
What should you do?
Question 60
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.