Question 61
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Question 62
You need to configure production control parameters for liquid cleaning solution manufacturing.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Question 63
A company plans to implement Dynamics 365 for Finance chain Operations.
You need to determine which manufacturing solutions to use.
Which manufacturing solution should you use? To answer, drag the appropriate setting to the correct drop targets. Each source may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Question 64
A process manufacturing company is implementing rebates in Dynamics 365 for Finance and Operations for some of their customers on specific items.
You are the production consultant in charge of implementing the processes needed for calculating and applying the rebates for the subset of customer and items.
You need to implement the order of transactions to process the rebates.
In which order should the actions be performed? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
Question 65
A company makes lubricants and greases used in the automotive industry.
They are planning to use Dynamics 365 Supply Chain Management to make products whose characteristics can be tracked throughout the production process and are associated with the packaged product.
You need to identify which production methodology to use.
Which production methodology should you use?