Question 6
Evaluation and mitigation of indoor air quality in an existing facility assessment would include participation by which of the following? Check the three that apply.
Question 7
Which four factors will most affect the choice of project delivery method? Check the four that apply.
Question 8
An architect is working on a large renovation project with an AIA B101 contract. The owner decides to contract separately with an electrical engineer and a security firm. The security firm asks the engineer and architect to coordinate the details for a new card reader access control system.
What is the first step the architect should take?
Question 9
A new site has been identified for a prototype fast food restaurant. The geotechnical report indicates fill materials were found in the subsurface conditions along the east side of the proposed building location.
What member of the project team should be involved in modifications to the prototype building design to address this issue?
Question 10
An architecture firm is negotiating a contract with an owner for a $2,000,000 project. The proposed architectural-only fee is 5% of the cost of construction through the end of the Construction Document Phase.
During the negotiations, the owner wants to apply for a building permit in 7 weeks without exceeding the original budget constraints. The project staff currently consists of 2 people who have an hourly rate of $100.
What is the minimum project staff required to meet the owner's new schedule?