Question 21
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?
Question 22
After construction begins, an owner asks the architect to select a different roof material. The architect wants to manage the risk associated with this change.
Question 23
The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents.
According to AIA B101, to which party should the architect report this observed deviation?
Question 24
An architect is evaluating a change order.
Where should the costs for the project superintendent or general foreman be included?
Question 25
What is the best method for an architect to reduce liability related to unknown site conditions?