Question 11
Your customer wants a projectstart date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this.(Choose the best answer.)
Question 12
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
AssociatedProject Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)
Question 13
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)
Question 14
You are now the project manager of a newly created implementation project. Which two items arenotpart of managing an implementation project?
Question 15
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contractLine 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task
30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)