Question 91
A company has completed a major project within time. cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment From the business analysis perspective, the main reason for this business failure was a failure to:
Question 92
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
Question 93
The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?
Question 94
A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?
Question 95
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs. Which project artifact could the test team review to help identify acceptance criteria?