Question 6
What is the transaction code for editing the planning profile?
Please choose the correct answer.
Response:
Question 7
You can maintain the following objects in the Project Builder. (4)
Question 8
Which of the following can be derived automatically when you carry out scheduling in projects with networks?
There are 2 correct answers to this question.
Response:
Question 9
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
Question 10
Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
There are 3 correct answers to this question.
Response: