Question 31
Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project.
Which of the following can be assigned?
There are 3 correct answers to this question.
Response:
Question 32
If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.
There are 2 correct answers to this question.
Response:
Question 33
Assume you have created a sales order for a material to which a strategy group for assembly processing has been assigned and the system automatically created a so-called assembly order in the background and started assembly processing.
In this case, the assembly processing omits which stage and generates an operative order directly from the sales order?
Please choose the correct answer.
Response:
Question 34
What are the different options available for project stock?
There are 3 correct answers to this question.
Response:
Question 35
Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.
In this scenario planned costs are determined for which of the following?
There are 3 correct answers to this question.
Response: