Question 31
Which role should be assigned to a user so they can read and retrieve data from any table of the Release Management application to generate reports?
Question 32
In which table can you find cost information for a specific fiscal period?
Question 33
Why is it recommended to keep the value of the property 'com.snc.project.task.max_task_duration' to 2600 or under?
Question 34
The Project Management application enables users to create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks. How many relationships can exist between two tasks?
Question 35
What is the demand workbench used for?
Choose 2 answers