Latest LEED-AP-BD-C Exam Premium Dumps provide by TrainingQuiz.com to help you Passing LEED-AP-BD-C Exam! TrainingQuiz.com offers the updated LEED-AP-BD-C exam dumps, the TrainingQuiz.com LEED-AP-BD-C exam questions has been updated to correct Answer. Get the latest TrainingQuiz.com LEED-AP-BD-C pdf dumps with Exam Engine here:
(407 Q&As Dumps, 40%OFF Special Discount: DumpsDB)
A project team is considering implementing a strategy that has previously been awarded as an Innovation credit on another project. Which actions should be followed if the project team wishes to gain formal pre-approval of the same strategy on the new project?
Correct Answer: B
Detailed To gain formal pre-approval for a strategy previously awarded as an Innovation credit, the project team must submit a Credit Interpretation Request (CIR) to the Green Business Certification Inc. (GBCI). This allows GBCI to evaluate whether the strategy meets the intent of LEED Innovation credits for the specific project context.
Question 332
During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?
Correct Answer: C
During preliminary energy analysis, massing and orientation are energy reduction strategies that can best help in reducing the energy load in the new building construction project. Massing and orientation refer to the shape, size, and direction of the building, which affect the amount of solar heat gain, daylight, and natural ventilation that the building receives. By analyzing the massing and orientation of the building, the project team can optimize the design to minimize the heating, cooling, and lighting energy demand, and enhance the thermal comfort and indoor environmental quality of the building. The LEED v4 Reference Guide for Building Design and Construction states that "the project team should use the results of the analysis to inform the owner's project requirements, basis of design, and design documents"1. The other options, such as green roof, site conditions, and programmatic and operational parameters, are not energy reduction strategies, but factors that influence the energy performance and demand of the building.
Question 333
Which of the following should be analyzed when pursuing an Integrative Design Process focusing on Energy-Related Systems?
Correct Answer: A
The correct answer is A, site conditions. According to theLEED V5: Building Design + Construction Guide, the Integrative Process Prerequisite, Integrative Project Planning and Design, requires the project team to perform a preliminary "simple box" energy modeling and analysis before the completion of schematic design. The purpose of this analysis is to evaluate the energy performance goals of the project and to identify and compare the energy-related design strategies.The analysis should include the following aspects1: Site conditions, such as climate, solar orientation, shading, and natural ventilation potential Massing and orientation, such as building shape, size, and orientation, and how they affect the heating and cooling loads, daylight availability, and passive design strategies Basic envelope attributes, such as insulation levels, window-to-wall ratio, glazing properties, infiltration rates, and thermal bridging Lighting levels, such as the target illumination levels, daylighting potential, and lighting power density Plug and process loads, such as the equipment and appliances that consume electricity, and their schedules and controls Programmatic and operational parameters, such as the occupancy, operating hours, and zoning of the building Thermal comfort ranges, such as the acceptable temperature and humidity levels for the occupants HVAC system selection, such as the type, efficiency, and control of the heating, ventilation, and air conditioning system The other choices are not aspects that should be analyzed when pursuing an integrative design process focusing on energy-related systems, because: Potable water availability is related to the water efficiency and water quality goals of the project, not the energy performance goals2. Acoustic performance of the project is related to the indoor environmental quality and occupant comfort goals of the project, not the energyperformance goals3. Applicability of green vehicles to the project is related to the location and transportation and greenhouse gas emissions goals of the project, not the energy performance goals4. :LEED V5: Building Design + Construction Guide, Integrative Process Prerequisite, Integrative Project Planning and Design, Option 1.Energy-Related Systems1;LEED V5: Building Design + Construction Guide, Water Efficiency Prerequisite, Indoor Water Use Reduction, Requirements2;LEED V5: Building Design + Construction Guide, Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance, Requirements3;LEED V5: Building Design + Construction Guide, Location and Transportation Credit, Green Vehicles, Requirements4
Question 334
The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because
Correct Answer: B
Explanation SRI generally decreases with age The Solar Reflectance Index (SRI) is a measure of the ability of a surface to reflect solar heat, as shown by a small temperature rise. It is calculated using the values of solar reflectance and thermal emittance of the surface. The higher the SRI, the lower the heat island effect. However, SRI generally decreases with age due to factors such as weathering, dirt accumulation, and biological growth. Therefore, the Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged SRI values for roofing material to ensure that the material maintains a high level of reflectance over time. References: * SpecTopics: Heat Island Reduction Credit and LEED V4/V4.1 - Carlisle SynTec1 * Solar Reflectance Index Measurements - Surface Optics Corp.2
Question 335
What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?
Correct Answer: C
Explanation According to the LEED Reference Guide for Building Design and Construction1, the Integrative Process Prerequisite, Integrative Project Planning and Design, requires the project to assemble an integrated project team that includes at least four key project team members, in addition to the owner or owner's representative. The key project team members are those who have the authority and responsibility to make design decisions and implement them during construction. The integrated project team should include professionals from different disciplines, such as architecture, engineering, landscape, interior design, construction, commissioning, operations, and maintenance. The integrated project team should collaborate throughout the project phases, from discovery to occupancy, to achieve the project goals and optimize the building performance. References: * LEED Reference Guide for Building Design and Construction v4 * Integrated Product Team (IPT) - AcqNotes * The Power of an Integrated Project Team Process - Little