Question 1
What is the relationship depicted between Activity G and Activity H?
Question 2
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?
Question 3
Which activity is drawn in the incorrect position?
Question 4
Total float is defined as the amount of time an activity can be delayed without impacting
Question 5
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):