Question 31
Which of the following is NOT required when performing weekly or monthly schedule updates?
Question 32
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
Question 33
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
Question 34
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Question 35
Determine the correct formula and date for the late finish for Activity 9004.