Question 6
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Question 7
Who will receive the most benefit from a master schedule of the Spring Highway project?
Question 8
EBS is an acronym for:
Question 9
What was the original planned duration for Activity A through Activity G?
Question 10
What changes to logic would eliminate Activity B from the critical path?