Question 21
Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
Question 22
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
Question 23
The data date or status date of a schedule represents the:
Question 24
What does the narrow band at "Y" represent?
Question 25
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?