Question 6
Which information Radiator can the team use best during the Sprint to track the work?
Question 7
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
Question 8
Your organization found that the Product Owner is consistently under more pressure than the developments and other participants in the project.
What is common solution for that?
Question 9
Company X-AppGo is very interested in getting the benefits of both the ITIL Framework and the Agile principles. They want to establish a disciplined service based approach, while reducing lead team in releasing application enhancements and improvements to their customer base.
Based on the above scenario, which would be the integrating Agile into the ITIL Framework?
Question 10
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?