Question 11
What is the main reason to limit Scrum Teams to 9 team members?
Question 12
Why is a Product Owner not allowed to define the workload of the Development Team for a new Sprint?
Question 13
Inexperienced Agile teams tend to overestimate how much they will achieve in the first Sprint.
Which project management activity will be most important in this case?
Question 14
During a Sprint Planning, a team has picked three User Stories:
Story 1 - 5 Story Points
Story 2 - 8 Story Points
Story 3 - 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
Question 15
After the creation of the Release Plan, the Product Owner says:
Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.
The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.
What are the other two factors?