Question 31
A customer created a public holiday on the 25-Dec-2018 (Tuesday) and assigned it to a geography to which an employee belongs to. However, the employees do not have a work schedule assigned. The employee records an absence from 24-Dec-2018 (Monday) to 26-Dec-2018 (Wednesday) using an absence type that measures duration in Days.
What will be the duration of the absence recorded?
Question 32
Which setup options must you use to implement discretionary disbursements on Absence Management?
Question 33
Which three types of Exceptions can be linked to a work schedule?